In section 1, brickwork is underway at the level of the 8th floor, and brickwork has begun on the 9th floor. The roof parapet is nearing completion.
Brickwork is being completed in sections 1 and 2.
Parking lot - 30% of the floor slab of the underground parking lot of the last level has been completed.