In section 1, the execution of the vertical elements of the 10th floor is completed. The floor slab of the 10th floor is being assembled
In section 2, the vertical elements of the 9th floor are completed.
In section 3, brickwork is being done at the level of the 6th floor. Work is being carried out on vertical elements on the 8th floor.