In section 1, vertical elements are performed at the level of the 13th floor.
In section 2, the floor slab of the 11th floor is pouring. Work on brickwork has begun at the level of the 9th floor.
In section 3 monolithic works are completed. Completed brickwork from the 3rd to the 7th floor.