PROGRESS OF CONSTRUCTION - FEBRUARY

13.02.2025
News image 1 News image 1
 

In section 1, the vertical elements are being made at the level of the 15th floor. Work on brickwork has begun at the level of the 7th floor.

In setion 2, the vertical elements of the 13th floor are made. Brickwork work is being carried out at the level of the 10th floor.

In section 3, monolithic works and brickwork on the residential floors have been completed.

 